Maharashtra's housing society redevelopment

Government of Maharashtra Issues New Housing Society Redevelopment Framework

PDF

Introduction

The Co-operation Department, Government of Maharashtra issued a new Government Resolution on September 30, 2026 (“2026 GR”), introducing a revised framework for societies undergoing redevelopment. The 2026 GR, issued under Section 79A of the Maharashtra Co-operative Societies Act, 1960 (“Act”) supersedes the earlier Government Resolution dated July 4, 2019 (“2019 GR”). Set out below is a comparative analysis of the 2026 GR with the earlier 2019 GR to aid stakeholders with understanding some of the key changes introduced by the 2026 GR.

Comparison of Key Changes under 2019 GR and 2026 GR

9.Approval of development agreementThe managing committee was required to approve the development agreement.The General Body Meeting of the Society shall now approve the development agreement.10.Bank guarantee to be given by developerThe terms to be included in the development agreement mentioned that the developer shall arrange for a bank guarantee to be given to the Society for an amount equal to 20% of the total cost of the redevelopment project.The General Body Meeting shall decide the extent and form of bank guarantee to be provided by the developer as a proportion of the total cost of the redevelopment project.11.Timeline for registration of permanent alternate accommodation agreement (“PAAA”)No specific timeline was mentioned for registration of PAAA with individual members under the 2019 GR.The PAAA with individual members shall be executed within 3 months after registration of the development agreement.12.Non-compliance of directions issued under Section 79A of the Act/Government ResolutionThe 2019 GR did not specifically mention any consequences in case of non-compliance of 2019 GR. However, Section 79A(3) of the Act provides that in case of non-compliance of directions issued under Section 79(A) of the Act by the concerned person (which included the 2019 GR), the Registrar may take action including removal of the members of the managing committee.The 2026 GR specifically mentions that in the event of non-compliance of 2026 GR, or if it is found that, in the redevelopment process, the members have been cheated, misled or subjected to any action detrimental to their interests, the concerned responsible office-bearers/committee members shall be liable for action under Section 78A/79A(3) of the Act including removal of such office-bearers/ committee members.

Sr. No. Topic 2019 GR 2026 GR
1. Quorum and majority required in first society general body meeting (“SGBM”) for undertaking redevelopment Quorum required in the first SGBM was 2/3rd of the total members of the society (“Society”). Consent of at least 51% of the total members of the Society was required for taking a decision for redevelopment. The threshold for quorum and consent of members is the same as mentioned in the earlier 2019 GR. The 2026 GR now permits that members who are abroad, critically ill, disabled or otherwise unable to attend may join through remote system/video conference (“VC”) and that they will count towards quorum and the 51% majority required for voting. However, physical attendance of 51% of total members of the Society is still mandatory.

In summary, the requirements for quorum and majority for undertaking the redevelopment are as mentioned below:

  1. Quorum required in the meeting shall be 2/3rd of the total members of the Society (including members attending through remote system/VC);
  2. Consent of at least 51% of the total members of the Society (including members attending through remote system/VC) is required for a decision for redevelopment; and
  3. Physical attendance of 51% of total members of the Society is mandatory.
2. Scope of project report expanded The architect/project management consultant was required to cover details in relation to Floor Space Index (“F.S.I.”) and Transferable Development Rights (“T.D.R.”) available in respect of the building and land of the Society in the project/feasibility report. In addition to the details of F.S.I. and T.D.R. available in respect of the building and land of the Society, the project report should cover the applicable rules of the City and Industrial Development Corporation, Mumbai Metropolitan Region Development Authority and municipal corporations, keeping in consideration the ownership of the land.

In addition, a separate project report and comparative statement is required to be prepared scheme-wise regarding benefits available under various schemes in the Development Control Regulations (DCPR/UDCPR) approved by the Government for the planning authority.

3. Timeline for meeting of Managing Committee after receipt of project report No specific timeline was mentioned in the 2019 GR. The secretary is required to convene a meeting of the managing committee within 30 days of receipt of the project report from the architect/project management consultant.
4. Approval of draft tender The managing committee was required to finalize the draft tender in a meeting of the managing committee. The draft tender shall now be presented before the members in the SGBM and approved by the majority of members at the SGBM.

The 2026 GR also mentions that a public tender notice must be published in leading local Marathi and English newspapers.

5. Timeline extended if fewer than three tenders received A first extension of at least seven days, followed by a second extension of seven days was to be granted in case less than three tenders were received from interested developers. The timeline for the first extension has now been increased to 15 days under the 2026 GR if fewer than three tenders are received from interested developers.

The timeline for the second extension remains the same as provided under the 2019 GR.

6. Timeline for appointment of authorized officer No timeline was mentioned in the 2019 GR. The Registrar shall decide on appointment of an authorized officer within 14 days from receipt of the proposal for appointment of an authorized officer along with the supporting documents from the managing committee as set out in Point 12(a) of the 2026 GR.
7. Quorum and majority required in next SGBM for selection of developer Quorum required in the meeting was 2/3rd of the total members of the Society. Consent of at least 51% of the total members of the Society was required for appointment of the developer. The threshold for quorum and consent of members required for selection of developer is now identical to the threshold required for undertaking redevelopment as set out in Point 1 above.
Service provider: For members attending through remote system/VC, the authorized officer shall make arrangements with the assistance of the service provider.
Voting mechanism: If at least one-fifth of the total members make a written demand, voting on the developer can be conducted through secret ballot instead of a show of hands.
8. Information to be provided to members All types of information in respect of redevelopment, such as notices, minutes of the meeting, project report etc. was to be made available on the website created by the Society. The requirement for a website has been removed. Instead, all documents (including video CDs/pen drives, tenders and draft agreements) must be open to members for free inspection. Copies of the documents must be given to the members upon request on payment of the prescribed fees.

Key Takeaways

The 2026 GR broadly makes the redevelopment process easier for members to take part in and more transparent. It also adds practical safeguards that protect members’ interests and brings uniformity to the redevelopment process. Failure to follow the process as set out under the 2026 GR may impact the process of appointment of a developer and, as a consequence, the entire process of redevelopment.


This insight has been authored by Avikshit Moral (Partner) and Preeti Dhar (Counsel). They can be reached on avikshit@snrlaw.in and pdhar@snrlaw.in, respectively, for any questions. This insight is intended only as a general discussion of issues and is not intended for any solicitation of work. It should not be regarded as legal advice and no legal or business decision should be based on its content.